Kitchen Remodel Cost Calculator

Assemble a kitchen budget by measured components instead of forcing cabinets, counters, flooring, appliances, and labor into one square-foot rate.

Formula reviewedJuly 24, 2026Inputs stay on your device
Enter your measurements
US customary units
Inputs stay on this device. Saved work syncs privately only when you choose to sign in; shared links include only the measurements in that link.
Option lab

Compare up to three scenarios

Capture the current result, change one or more inputs, and see the options side by side. The first option becomes your baseline.

0/3 in this page session

Your live calculator remains unchanged. Capture it only when you want a comparison point.

Saved comparisonsKeep an option set on this device and resume it later.
0 saved
Device-local project

Save this estimate as a project section

Name rooms, roof planes, yard areas or other sections separately. CalcurHome will combine compatible results from this calculator on this device.

No account or personal information required. Data remains in this browser until you delete it or clear browser storage.

View all saved project estimates

Embed this calculator

Add the live, responsive calculator to an HTTPS website. Visitors can change measurements inside the embed; the full CalcurHome page remains the source for formulas, guidance and limitations.

Preview embed

01

What does the kitchen remodel cost calculator calculate?

Price cabinets by planned linear feet, countertops and flooring by measured square feet, then add entered appliance, labor, and permit allowances. Apply contingency only after those components are visible. The estimate excludes any item left at zero and cannot replace drawings or bids for layout, utilities, structure, ventilation, finishes, tax, and schedule.

02

Component-based kitchen remodel budget

Total = (cabinet feet × rate + countertop area × rate + floor area × rate + appliances + trade work + fees) × contingency factor

Each measurable finish uses its own purchasing unit, while appliances, remaining trade work, and fees are project allowances. Keeping components separate exposes omissions and prevents a cabinet quote from being treated as though it prices the entire room.

03

How to measure for an accurate estimate

  1. Develop a dimensioned plan showing walls, openings, cabinet runs, islands, appliances, sinks, clearances, utilities, and ventilation route.
  2. Measure countertop pieces along the planned cabinet layout and identify depth, edges, seams, cutouts, backsplash, and supports.
  3. Measure finished flooring area and state whether material continues beneath cabinets or appliances and who handles subfloor preparation.
  4. Request coordinated cabinet, appliance, plumbing, electrical, lighting, ventilation, finish, demolition, and permit scopes before comparing totals.
04

Component budget for a mid-size kitchen

The plan has 20 cabinet feet at $600, 50 countertop square feet at $80, 200 floor square feet at $12, $6,000 appliances, $15,000 trade work, $1,000 fees, and 10% contingency.

The entered subtotal is $40,400 and the kitchen planning total is $44,440.
05

Before you purchase material

  • Lock appliance specifications before cabinet and utility rough-in because clearances, panels, power, gas, water, and ventilation can differ.
  • Compare cabinet quotes by construction, finish, hardware, accessories, panels, fillers, trim, delivery, installation, and field measurement.
  • Use countertop proposals that identify material, slab allocation, thickness, edges, seams, cutouts, sink work, supports, template, and installation.
  • Keep allowances realistic and selection deadlines visible; late products and substitutions can disrupt both price and construction sequence.
06

Common questions

Why not price a kitchen only by floor area?

Cabinet length, island size, countertop area, appliance package, utility relocation, ventilation, and finish quality drive kitchen cost more directly than open floor area. Component pricing reveals those decisions and makes two layouts of the same room size meaningfully comparable.

What belongs in other construction and trade quotes?

Use it for documented work not captured by cabinets, counters, flooring, appliances, or fees, such as demolition, framing, drywall, painting, plumbing, electrical, lighting, ventilation, backsplash, and finish carpentry. Keep an itemized worksheet behind the entered total so omissions remain visible.

Should appliance cost include installation?

Include delivery, installation, connection kits, panels, trim, haul-away, tax, and required electrical, gas, plumbing, or ventilation changes only when the allowance actually covers them. A retail appliance price alone may omit substantial site and trade work needed for operation.

How should I compare kitchen contractor bids?

Give bidders the same plan, cabinet and appliance schedule, finish specifications, allowances, demolition limits, utility scope, permit responsibility, and schedule. Compare itemized inclusions, exclusions, alternates, warranties, payment milestones, and change-order terms instead of using the lowest headline total.

07

Sources and reference standards

Project workflows

Use this result in a complete project plan

Kitchen and bath planner

Kitchen and bathroom projects concentrate cabinetry, appliances, plumbing, ventilation, electrical work, waterproofing and detailed finishes into small areas. A broad price per square foot can conceal those decisions and double-count shared demolition or trade mobilization. This guide builds a coordinated existing-condition record, room-specific component budgets and one explicit project-level scope using only prices or quotes the visitor enters.